WE RECONSTRUCT A CABLE LINE IN DNIPRO

Installation engineers of the specialized EDS E-Cable team are reconstructing a 0.4 kV cable line in the city of Dnipro - from a transformer substation (TP-718) to the trauma department of city hospital No. 2, and then to a residential building.

30.09.2020
EDS Engineering
EDS COMPLETED THE RECONSTRUCTION OF THE 35/6 KV SS SEVERNAYA

The EDS team carried out the technical re-equipment of the 35/6 kV SS Severnaya in Zhovti Vody city (Dnipropetrovsk oblast). The whole complex of works took 26 days.

22.09.2020
EDS Engineering
IN THE DNIPRO POLYTECHNIC NTU AN EDUCATIONAL LABORATORY WAS OFFICIALLY OPENED WITH THE SUPPORT OF THE EDS

The solemn opening of a modern laboratory of smartgrid technologies took place at the Department of Electrical Power Engineering of the Dnipro Polytechnic NTU. EDS as a #responsible_business undertook the complete renovation of the premises in new corporate colors, arrangement of modern furniture, with which it is convenient to perceive complex topics and all the existing electrical switchboard "stuffing" of high and medium voltage classes - from the X-Line input-distribution device to the telemechanics cabinet with an integrated ASKОE (automated system of power consumption monitoring and accounting) module based on SCADA.

21.09.2020
EDS Engineering
We are reconstructing the 150/6 KV SS for YUZHNIY GOK (South Mountain Concentrating Combine)

The EDS Engineering has started the technical re-equipment of high-voltage electrical substation PS YuGOK 150/6 kV in the city of Kryvyi Rih, the Dnipropetrovsk oblast. During the work, the oil circuit breaker VMG-133 will be replaced with vacuum one, as well as the secondary wiring diagram in the F-626, F-636, F-637, F-638, F-639 cells will be modernized.

16.09.2020
EDS Engineering
UNFREEZING. EDS IS BUILDING A NEW LARGE SPS

he EDS Group has started the turnkey construction of a new industrial solar power station with a capacity of 9.99 MW in the Zaporizhia oblast. The future SPS will be built in the area of Dniprorudne city, Vasylivskyi district, Zaporizhia oblast.

09.09.2020
EDS Engineering
Reliability and safety. EDS renewed the supports and mounted the reclosers

The EDS team has installed new supports in the range of 6, 10 kV lines and mounted 17 10 kV 1000A reclosers on them. As of today, all reclosers have been installed, the project was completed on time.